A conditional lien waiver gives up your lien rights for a payment only once that payment has reached you and cleared. An unconditional lien waiver gives them up the moment you sign it, whether or not the money ever arrives. Sign the conditional one to get paid, and the unconditional one after the funds are in your account.

By SignThis · Published · 8 minute read

The four kinds of lien waiver

Every lien waiver is the answer to two questions: does it wait for the money, and does it cover one payment or the whole job?

Progress (also called partial or interim)Final
ConditionalSigned before a progress payment clears. Takes effect once that payment is received, for work through the through date.Signed before the last payment, including retainage, clears. Takes effect once it is received, for the whole job.
UnconditionalSigned after a progress payment has cleared. Takes effect on signing.Signed after the final payment has cleared. Takes effect on signing and ends your lien rights on the job.

The names change from state to state. Michigan's statute calls them partial and full waivers; Georgia's forms say interim and final. The two questions stay the same.

What "conditional" actually changes

The condition is payment. A conditional waiver handed over with your pay application releases nothing until the check or transfer named in it has been received and the funds are in your account. If the check bounces or the payer stops it, the waiver has no effect and your lien rights stay where they were.

An unconditional waiver works like a receipt. It states that you have been paid and gives up the rights as soon as you sign, so it belongs only on money that has already landed.

A drywall subcontractor shows how the two fit together. On the 25th it bills $18,500 for work through the end of the month. The general contractor will release the check on Friday but wants a waiver first, so the sub signs a conditional progress waiver for $18,500 through the 31st. The check is deposited on Monday and clears on Wednesday. With next month's pay application, the general contractor asks for an unconditional waiver for that $18,500, and a fresh conditional one for the new bill.

Which waiver to sign, and when

  1. You send a pay application: a conditional progress waiver for that application's amount and through date.
  2. That payment clears: an unconditional progress waiver for the same amount and date, if the payer asks for one. Many hand it over with the next pay application.
  3. You bill the last payment, including retainage: a conditional final waiver.
  4. The final payment clears: an unconditional final waiver.

A simple rule follows: the word "unconditional" goes only on a document for money already in your account. And a final waiver goes only on the last payment, because it releases retainage and every unpaid extra along with it.

The risk of signing an unconditional waiver before the money clears

A mechanic's lien ties your unpaid bill to the property itself, which is why owners and lenders take it seriously. Sign an unconditional waiver for a payment that does not arrive and you have generally given up that lien, and usually any payment bond claim, for the work and amount it names. What remains is an ordinary claim for the debt against whoever hired you, which is worth only as much as that company's ability to pay.

California states the danger on the forms themselves. Its unconditional waivers open with a notice telling the claimant the document is "enforceable against you if you sign it, even if you have not been paid" (California's unconditional progress form). Some states soften the blow in particular cases: in Nevada, for example, a waiver given for a check that fails to clear is void under the statute. Rules like that are narrow and differ from state to state.

Georgia adds a twist from the other side. There, a waiver in the statutory form is treated as paid after a set number of days unless the claimant files an affidavit of nonpayment, or a claim of lien, in time, so a Georgia waiver for money that has not arrived needs a date in your calendar.

If a payer insists on an unconditional waiver before paying, the usual answers are a conditional waiver now and an unconditional one after the funds clear, or payment by wire at the moment you sign.

States that set lien waiver wording by statute

In these states the statute sets out the waiver wording; each row says what that means for a waiver written another way. Each was checked against the statute or the state's own page on November 18, 2026.

StateWhat the law saysSource
ArizonaA waiver is unenforceable unless it follows substantially one of four statutory forms (conditional or unconditional, progress or final).A.R.S. § 33-1008
CaliforniaA waiver must follow substantially one of the four forms in Civil Code sections 8132, 8134, 8136 and 8138.Contractors State License Board
GeorgiaInterim and final waivers must substantially follow the statutory forms, and lien rights cannot be waived before the work or materials are furnished.O.C.G.A. § 44-14-366, as amended by SB 315
MichiganWaivers are to be made in substantially one of four statutory formats: partial and full, each conditional or unconditional. A waiver required in advance of the work is invalid except to the extent payment was actually made.MCL 570.1115
NevadaA waiver is unenforceable unless it is in one of four statutory forms, and the unconditional forms must carry a notice in large type.NRS 108.2457
TexasA waiver is unenforceable unless it substantially complies with one of the forms in Property Code section 53.284. For original contracts made on or after January 1, 2022, it no longer has to be notarized.Tex. Prop. Code § 53.284 and HB 2237
FloridaThe statute gives sample progress and final forms, and a payer may not require a waiver that differs from them. Lien rights cannot be waived in advance.Fla. Stat. § 713.20

Other states have forms of their own, and legislatures amend lien laws often, so read the statute for the state where the property is, not where your company is. A few states, and some lenders and title companies, also want the waiver notarized. An electronic signature is not a notarization.

Lien waiver or lien release?

The two are often mixed up. A lien waiver gives up the right to file a lien for work that has been paid for, usually before any lien exists. A lien release generally cancels a lien that has already been recorded against the property, and it is usually recorded in the same county office. Some states blur the names: California's forms are titled "waiver and release".

Signing a lien waiver electronically

In the US, the federal ESIGN Act and state UETA laws generally give electronic signatures the same effect as handwritten ones. The state's wording rules still apply to what the waiver says, and a notarization requirement still needs a notary.

SignThis is for electronic signatures, and it fits the moment a waiver changes hands: a general contractor sends the waiver as a PDF with the payment request, the subcontractor signs it on a phone from the job site without creating an account, and both are emailed the sealed PDF, or a private link to it, with its audit certificate before the check goes out. The free conditional lien waiver template is the conditional progress kind, with a note on each section. In a state with its own form, fill in that form, save it as a PDF and send it the same way. Contractors who collect a waiver from every sub each month will find more on the general contractors page.

The free plan includes 3 documents a month. Send a lien waiver for signature.

Common questions

What is a lien waiver?

A signed statement from a contractor, subcontractor or supplier giving up the right to file a mechanic's lien, and usually bond and payment claims, for work it has been paid for. Owners, lenders and general contractors collect one with each payment because an unpaid sub or supplier can otherwise lien the property even after the owner has paid the general contractor.

Is a partial lien waiver the same as a conditional one?

No. "Partial" (or progress) is about how much the waiver covers: one payment, through one date. "Conditional" is about when it takes effect: once the payment clears. A partial waiver can be conditional or unconditional.

Does a lien waiver need to be notarized?

In most states it does not. Texas dropped its notarization requirement for original contracts made on or after January 1, 2022. A few states still require it, and some lenders and title companies ask for it anyway, so check before you sign.

Can a contract make me waive my lien rights before I start?

Many states do not allow it. Florida's and Georgia's statutes say lien rights cannot be waived in advance, Michigan's makes such a waiver invalid except to the extent payment was made, and Arizona's enforces a written waiver only if it is one of the statutory forms or the claimant has been paid in full. Check your state before signing a contract with that clause.

Does signing a progress waiver mean I have been paid in full?

No. It covers only the amount and through date it names. List anything still owed for that period, such as unpaid change orders, disputed items or retainage, in the exceptions so it is not swept in. For the electronic side of the question, see are electronic signatures legally binding. This article is general information, not legal advice.