How-to guide
How to write a change order your client signs before the extra work
Write one change order for each change and number it for the job. Name the signed contract it changes, describe the work added, removed or swapped with quantities and locations, give the reason, the amount added or deducted, the contract price before and after, the days added and the new finish date, and when it is paid. Both of you sign before the extra work starts.
Checked November 26, 2026
Watch: how to write a construction change order
Steps at a glance
- Number it and name the contract it changes
- Describe the change so anyone could check it
- Write the reason in one line
- Price the change the way you price a bid
- Carry the running total
- Add the days and the new finish date
- Say when the change is paid
- Send it for both signatures
- Start the extra work once both have signed
Other ways below: Worked example: heated floor added to a bath remodel · On your own form, uploaded and sent
What you need
- The date of the signed contract or approved estimate this change amends
- The current contract price, counting every change order already signed
- Your price for the change: materials, labor, any subcontractor and your markup
- Your client's email address, and the co-owner's if two people signed
Way 1 of 3
Line by line, in the free template
Best when: Your client asked for extra work, or you found something the price did not cover, and the job already has a signed contract.
Number it and name the contract it changes
Open the change order template, give this change the next number on the job and add today's date. Use the customer's and your business's names exactly as the contract has them, then the contract's date, the project and the job site address.
Started from a signed estimate approval? Use the date it was approved. No signed paper at all? Write the contract first.
Describe the change so anyone could check it
Say what is added, removed or swapped, with quantities, sizes, locations, product names and model numbers. Then name any follow-on work the price leaves out, such as repainting a wall you have to open.
Keep to one change per order, so the client can approve one and refuse another.
Write the reason in one line
Record who asked for it or what forced it, and when: the homeowner's request on site, a hidden condition found during demolition, an inspector's correction or a product that went out of stock.
Price the change the way you price a bid
Add up materials, your crew's labor, any subcontractor's price and your markup for overhead and profit, unless the contract fixes the markup on changes. For removed work, write the credit as a deduction; for a change that only moves the date, write no change.
A credit for removed work can be less than its line in the original price if you already bought the materials.
Carry the running total
Write the contract price before this change: the original price plus or minus every earlier signed change order. Then write the price after it, so the newest signed change order shows what the whole job costs today.
Add the days and the new finish date
Count the working days the change adds, including waits for a special order or another inspection, and write the new estimated completion date. A change that costs nothing can still move the finish, and this line is where both of you agree it.
Say when the change is paid
Pick one: with the next progress payment, or when the changed work is finished. A credit comes off the next payment due, which the template's payment section already says.
Send it for both signatures
On the template page choose Send this for signature, fill in the blanks and press Open in the editor. Add the customer, then yourself as the Contractor, press Place signature blocks, then Review & send and Send for signature. Sign your part with Sign now.
Two owners signed the contract? Add the second one as a signer as well; that person gets a signature block to drag into place.
Start the extra work once both have signed
The template holds the changed work until both signatures are in, with room for emergency steps that prevent injury or damage. When the client signs, everyone gets the sealed PDF and its audit certificate: file it with the contract and bill from the new total.
Way 2 of 3
Worked example: heated floor added to a bath remodel
Best when: You want to see every line of a change order filled in with real figures before you write your own.
The job so far
A hall bath remodel signed on February 10 for $24,500. Change order 1, a shower niche for $650, was signed on February 20. On March 3, after demolition, the homeowners ask for heat under the new floor tile.
Number, date and contract
Change order 2, dated March 4, between the two homeowners and the contractor's business, changing the contract of February 10 for the hall bath remodel at the job site address.
The change and the reason
Install an electric heating mat under the new floor tile, about 40 square feet, with a programmable thermostat beside the door and a new dedicated circuit from the panel. No heat under the tub or vanity. Reason: the owners' request on site, March 3.
The price, worked out
Mat, thermostat and wire $820, the electrician's price $480 and the crew's labor $500 make $1,800. Markup for overhead and profit at 15 percent adds $270, so the line reads: add $2,070.
The running total
Contract price before this change: $25,150, which is the original $24,500 plus change order 1's $650. Contract price after this change: $27,220.
Time and payment
Add 2 working days, one for the new circuit and one waiting for the thermostat, so the new estimated completion is March 27. Payment is due with the next progress payment, when the tile is finished.
Signatures, then the work
Both homeowners and the contractor sign it on March 4. The electrician runs the circuit only after the third signature is in, and the next invoice starts from $27,220.
Way 3 of 3
On your own form, uploaded and sent
Best when: Your contract names its own change order form, or your estimating software already prints change orders you like.
Fill in every line
Complete the same lines on your form: number, contract date, the change, its reason, the amount, the price before and after, the days added and when it is paid. Keep any wording your contract requires.
Save it as a PDF or a Word file
Export or save the change order as a PDF. A Word file (.docx) works too: the browser turns it into a PDF you check page by page before placing blocks.
Upload it and add who signs
Open send a document, upload the file and add the customer and yourself as signers with your email addresses. Add a second owner if the contract has one.
Place the blocks and send it
Press Detect fields to put blocks on your form's signing lines, or Place signature blocks, and check where they landed. Then choose Review & send and Send for signature. Your first 3 documents each month are free.
Other ways people ask
How to write a change order request
A change order request is the priced change before anyone has approved it. Write it on the same form with every line filled in and send it; it becomes the change order once both of you sign. When the client is choosing between options, price each one as its own request.
How to write a change order for a credit
Use the same form with the amount as a deduction, such as deduct $560, so the price after comes out lower than the price before. Describe the removed work as exactly as you would added work, and allow for materials already bought before you set the credit.
How to write a change order that only moves the date
Write no change on the price lines, fill in the days added and the new completion date, and give the reason, such as a supplier's delay. Both signatures fix the new date, so finishing late is measured against a date the client agreed.
How to write a change order for a subcontractor
When the owner's change reaches a trade, write a second change order between you and the sub for its share of the scope, price and days, under the subcontractor agreement. Get it signed before the sub starts, as general contractors do with pass-down changes.
How to write a change order when the cost is unknown
When nobody can see how far rot or damage goes, write the change as time and materials at stated rates with a not-to-exceed figure, and require a new signed change order before going past it. Swap in a fixed amount once the extent is known.
If something goes wrong
- The client said yes by text and now disputes the amount
- Send the change order with the figure from the text and pause that part of the work until it comes back signed. From then on, answer requests on site with a priced change order rather than a number in a message.
- Nobody can say what the job costs after six changes
- Fill in the before and after prices on every change order, in number order, so the latest signed one carries the current total. If earlier ones left it out, add them up once and put that total on the next change order.
- Only one of the two homeowners signed the change order
- Send it again with both owners as signers before the changed work goes on. Whoever signed the original contract signs its changes too, or someone they have authorized in writing.
- The change needs a special-order part and the finish date slips
- Put the lead time in the days line when you price the change, not afterward. If the date moves later for a reason outside the change, write a time-only change order with no change to the price.
- The client won't sign but wants the extra work done
- Keep working on the original scope and leave the changed part alone. Ask what is holding it up; when it is the price, a second option on a new change order request often settles it.
Worth knowing
Some states set what a home improvement change order must say. In California, one becomes part of the contract only once it is in writing and signed by both parties before its work starts, and it cannot be enforced against the buyer unless it states the scope of work, the amount added or subtracted, and its effect on progress payments or the completion date (Business and Professions Code 7159 and 7159.6). Rules differ by state; this is general information.
Questions
Should a change order show my markup?
Show the total for the change; a breakdown by materials, labor and markup is optional unless your contract asks for one. Many contracts set the overhead and profit allowed on changes, so read that clause before you price. A breakdown helps with a client who doubts the figure.
Can I put several changes on one change order?
You can, as long as each change has its own description, price and days, with one total at the end. Separate orders are easier to manage: the client can approve one and turn down another, and each price stays clear if anyone questions it later.
How should I number change orders?
Start at 1 on each job and go up in order, whatever the size of the change, so a gap in the numbers shows a missing one. A request the client turned down can keep its number, marked declined, so the sequence stays whole.
Who writes the change order, the contractor or the client?
Usually the contractor, who knows the price and the days, writes it and sends it, and the client reviews and signs. Either side can propose a change, and the construction contract template says so in its section on changes.
Can a change order be signed electronically?
Generally, yes. Under the federal ESIGN Act (15 U.S.C. 7001), a contract may not be denied legal effect solely because an electronic signature was used to form it, and state UETA laws say much the same: Wisconsin's electronic transactions law (section 137.15) lets an electronic signature meet a law's requirement for a signature. Follow any approval steps your contract sets.